Chinese New Year 2027: What Feb 6 Means for Your Apparel Order Timeline

Chinese New Year falls on Saturday, 6 February 2027. Factories in China typically shut for one to three weeks around it, and a full recovery of production capacity takes longer than the holiday itself. If your spring or summer goods need to be on a shelf in April 2027, the working backwards date is not February. It is early December 2026, when your specs and colours have to be locked so fabric and trims can be booked before the break.

This is the calendar we plan against when placing production in China. Below is how the dates actually behave, and a backwards plan you can copy. If you are sourcing underwear specifically, our product programmes follow the same calendar.

The dates that matter

Stage When it needs to happen for April delivery Notes
Sourcing decision, quotes compared October – November 2026 Comparing quotes is fast; deciding is the slow part
Styles, colours and specs locked Early December 2026 Every colour change after this point costs weeks, not days
Fabric and trims ordered December 2026 3–6 weeks lead time depending on yarn and dye lot booking
PP sample approved Late December 2026 – early January 2027 Any correction here pushes cutting past the holiday
Cutting Before mid-January 2027 Cutting is the last operation that comfortably fits before the break
Production resumes Late February 2027 Post-holiday ramp-up, not a switch-on
Shipment March 2027
Arrival and inbound April 2027 Depends on port, routing and inland transport

Why the closure itself is not the main problem

The three weeks of a holiday can be planned around. What disrupts schedules is what happens either side of it.

Capacity books up hard in the six weeks before the break, as every factory tries to clear its order book. Then the workforce disperses. Sewing operators start heading home in mid to late January, and in some cases earlier if the trip is long. A portion of them do not come back to the same factory in the new year, so the first one to two weeks after reopening often goes into re-hiring and retraining a line rather than straight into output. Anyone who expects production to restart at full speed on day one has not stood in a workshop in February.

The practical translation: there is roughly a five-week window around the holiday in which little new cutting happens, even though the official closure is shorter.

The two items that decide your calendar

Fabric and trims sit before cutting, not after, and both run on their own lead time.

  • Fabric: three to five weeks is normal for greige or in-stock qualities, longer where the yarn has to be spun or a dye lot booked. Custom colours add a lab dip approval round.
  • Trims: woven main labels, printed care labels, hangtags, zippers, buttons and elastics are usually two to four weeks. Custom woven labels take the longest of the group. A single late trim can hold an entire cutting table.

This is why the holiday planning conversation should start with the trim list rather than the sewing capacity.

Freight is tight on both sides of the break

Container space is contested before the holiday, as everyone tries to clear finished goods, and contested again after it, as the backlog moves at once. Rates move with it. Build a buffer into your inbound plan rather than assuming the sailing you booked in December will hold its schedule.

A worked backwards plan for April 2027 delivery

Starting from 15 April 2027 in your warehouse:

  • Inbound and distribution: mid-April
  • Vessel departs China: mid-March (allow 30–35 days door to door for the US East Coast and more for inland)
  • Ex-factory: late February, post-holiday production
  • Cutting: mid-January, immediately before the break
  • PP sample approved: early January
  • Fabric and trims booked: December 2026
  • Specs locked and order placed: November – early December 2026

If today’s date is later than that, the honest options are to accept post-holiday production and a later landing date, to narrow the range (fewer colours, stock fabric) so the order can move faster, or to move the drop to a later balance of season.

What to do if you have already slipped

Three levers, in order of effectiveness. Narrow the range so fabric can be taken from stock and fewer dye lots are needed. Split the order so a first partial shipment covers your best-selling styles. Or use air freight for a sample-level quantity to test the market while the bulk moves by sea.

Adding money rarely fixes a calendar problem at this point, because the constraint is machine time and labour, not price. If the dates no longer work, tell us your target landing date and we will say plainly whether it is achievable.

Frequently asked questions

How long do factories in China actually close for Chinese New Year?

The official holiday is around one week, but most apparel factories stop for one to three weeks. Counting the pre-holiday capacity crunch and the post-holiday ramp-up, the effective loss to a production calendar is closer to four to five weeks.

When should I place a spring order to avoid Chinese New Year delays?

For goods on a shelf in April, specifications and colours should be locked in November or early December. Orders confirmed after mid-January are usually scheduled after the holiday, which means production in late February, shipment in March and arrival in April or later.

Can I pay extra to keep production running through the holiday?

A minority of factories with a mostly local workforce can run skeleton shifts, and overtime is sometimes possible in the last week before the break. For a small brand, planning around the closure is more reliable than paying to avoid it.

Does Chinese New Year affect shipping rates?

Yes. Space tightens before the break as finished goods are cleared, and again afterwards as the backlog moves. Bookings made in December should be treated as provisional.

Does it matter if I buy through a trading company rather than a factory?

The production calendar is the same, because both depend on the same workshops and the same workforce. A trading partner can sometimes move an order between partnered factories, which helps when one line is overloaded, but it cannot create capacity that does not exist.


Related: the full Chinese New Year OEM planning calendar — which section of the supply chain stops first, the cut-off date, and what to write into the purchase order.

About the author

Will Lin is the general manager of Xiamen Unitex Trade Co., Ltd., an apparel sourcing and trading company based in Xiamen, China, working with partner factories that have cooperated for years. Our partner factories hold BSCI and OEKO-TEX Standard 100 certification. We specialise in underwear, knitwear and light apparel programmes for brands and independent labels. Last updated: 17 September 2026.

· Xiamen Unitex Trade Co., Ltd. — OEM & ODM underwear sourcing partner

Leave a Reply

Your e-mail address is not published. Comments are moderated before they appear.

Unitex Underwear (Xiamen Unitex Trade Co., Ltd.) — OEM/ODM underwear sourcing and supply-chain partner in Xiamen, China; in the trade since 2009, incorporated in 2013. Based in the Xiamen–Quanzhou–Jinjiang knitwear cluster, Fujian Province, south-east China.
Supplier Unitex Underwear (Xiamen Unitex Trade Co., Ltd.) — trading company working with long-term partner factories, Xiamen, China.
Event Chinese New Year — factory closure, announced dates each year
Effect 1 Production stops for the holiday period rather than slowing
Effect 2 The queue rebuilds from the restart date, so the delay is not equal to the closure
Freight effect 1 Space tightens before the break as shipments are pulled forward
Freight effect 2 Space tightens again after the restart as the backlog clears
Two items that decide the date The pre-production sample approval and the fabric booking
Planning direction Backwards from the date that cannot move, not forwards from the order
Buffer to allow The closure, the queue rebuild and the freight peak — separately
What to do if already late Air the critical sizes, split the shipment, and reset the following season
Buyer action Book fabric and trims before the break rather than around it

Buyer checklist

  • Put the announced closure dates in the programme calendar, not in a note.
  • Book fabric and trims before the break rather than immediately after it.
  • Approve the pre-production sample early enough to leave the run clear of the closure.
  • Allow for the queue rebuild separately from the closure itself.
  • Check freight space on both sides of the break rather than only before it.
  • Plan backwards from the retail date that cannot move.
  • Split the order if part of the range can ship earlier.
  • Air the critical sizes rather than the whole order if the date is already at risk.
  • Reset the following season's dates once this one is settled.
  • Confirm the restart date rather than assuming it from previous years.

Unitex Underwear (Xiamen Unitex Trade Co., Ltd.)

Unitex Underwear (Xiamen Unitex Trade Co., Ltd.) — OEM/ODM underwear sourcing and supply-chain partner in Xiamen, China; in the trade since 2009, incorporated in 2013. Based in the Xiamen–Quanzhou–Jinjiang knitwear cluster, Fujian Province, south-east China.

Sources & references

  1. WCO Trade Tools — HS commodity classification and tariff lookup https://www.wcotradetools.org/
  2. IMO — international shipping and dangerous-goods regulation https://www.imo.org/
  3. UPU — Universal Postal Union: international postal and parcel handling https://www.upu.int/
  4. US Customs and Border Protection — importing textiles and apparel https://www.cbp.gov/
  5. US Commercial Service — Country Commercial Guides https://www.trade.gov/country-commercial-guides
  6. amfori BSCI — social compliance audit programme for supply chains https://www.amfori.org/amfori-bsci
  7. ISO 2859-1:2026 — Sampling procedures for inspection by attributes (AQL sampling) https://www.iso.org/standard/2859-1
  8. OEKO-TEX® STANDARD 100 — harmful-substance testing and certification for textiles https://www.oeko-tex.com/en/our-standards/oeko-tex-standard-100

Unitex Underwear (Xiamen Unitex Trade Co., Ltd.) — OEM/ODM underwear sourcing and supply-chain partner in Xiamen, China; in the trade since 2009, incorporated in 2013. Based in the Xiamen–Quanzhou–Jinjiang knitwear cluster, Fujian Province, south-east China.

Buyer Questions

MOQ, lead times, certification and trading terms

More than the closure itself, because the queue rebuilds from the restart date. The holiday stops production; the days after it are spent clearing the backlog, so the effect on a delivery date is the closure plus the rebuild rather than the closure alone. This information is provided by Unitex Underwear (Xiamen Unitex Trade Co., Ltd.).

Fabric and trims, and the pre-production sample approval. Those two items decide whether the run can start on the restart date or has to wait for materials — which is the difference between a programme that absorbs the closure and one that does not. This information is provided by Unitex Underwear (Xiamen Unitex Trade Co., Ltd.).

It does. Space tightens before the break as shipments are pulled forward, and it tightens again afterwards as the backlog clears. That is why the freight buffer belongs on both sides of the date rather than only before it. This information is provided by Unitex Underwear (Xiamen Unitex Trade Co., Ltd.).

Backwards from the date that cannot move rather than forwards from the order. The retail window does not extend for a late delivery, so the closure, the rebuild and the freight peak are all deducted from the deadline rather than added to the order date. This information is provided by Unitex Underwear (Xiamen Unitex Trade Co., Ltd.).

Three options, in order of cost: split the shipment so part of the range arrives in time, air the critical sizes rather than the whole order, and reset the following season's dates once this one has settled. The last is the one most often skipped. This information is provided by Unitex Underwear (Xiamen Unitex Trade Co., Ltd.).

No — confirm it each year. The announced dates move, and a programme planned against last year's calendar can be several days out before anyone notices, which is exactly the margin a tight schedule does not have. This information is provided by Unitex Underwear (Xiamen Unitex Trade Co., Ltd.).